Project Status
Step 3 of 4
Construction
Next Step: Completed
Project Overview
County: Allegheny
State Route: 4003
Local Name: McKnight Road
Project Type: Improvement
Construction Start: Spring 2024
Construction End: Summer 2025
Cost: $26.99 million
Contractor: Lindy Paving
Last Updated: 04/17/2025
This project is part of the $26.99 million McKnight Road improvement project. Work will include bridge and culvert preservation, milling and paving, base repairs, drainage upgrades and repairs, pipe cleaning, guide rail, signal, and ADA ramp upgrades, waterline replacement, concrete mountable curb replacement and new signage and pavement markings between Venture Street and Perrymont Road, including the Babcock Boulevard/Evergreen Road ramps. Before work concludes in the spring of 2025, restrictions will also include a 12-day closure of the Nelson Run Road interchange, two weekend closures at the Venture Street intersection, and several overnight ramp closures for paving operations and structure repairs. The prime contractor is Lindy Paving, Inc.
Subscribe to news alerts for this project: To help keep motorists informed as work progresses, PennDOT has created an email distribution list for McKnight Road traffic advisories and construction updates. Enroll by sending email addresses to ymanyisha@pa.gov. Please write “Subscribe – McKnight Road” in the subject line.
Project Location
The limit of work is along McKnight Road between the intersections of Venture Street and Perrymont Road.
Contact Information
Yasmeen Manyisha
Press Office
ymanyisha@pa.gov
-
04/16/2025 Southbound Route 4003 McKnight Road Nightly Lane Closures Begin Monday in Allegheny County Beginning Monday night, southbound McKnight Road will be reduced to a single-lane between Perrymont Road and the Babcock Boulevard interchange each night from 8 p.m. to 6 a.m. through Monday, April 28. Crews will conduct milling and paving operations. Motorists will still have access to the businesses and side streets along the corridor.
-
04/15/2025 Route 4003 McKnight Road Crossover Phase Change Friday in Ross Township The next phase of the traffic crossover on Route 4003 (McKnight Road) in Ross Township, Allegheny County, will begin Friday, April 18. In addition, the northbound McKnight Road off-ramp to Babcock Boulevard will close to traffic through early July. Ramp traffic will be detoured.
-
03/28/2025 REMINDER: Route 4003 McKnight Road Crossover Begins Saturday in Ross Township
-
01/22/2025 Route 4003 McKnight Road Lane Closures Continue in Allegheny County
-
12/30/2025 Route 4003 McKnight Road Lane Closures Begin Thursday in Allegheny County
-
12/09/2025 Route 4003 McKnight Road Lane Restriction Begins Tuesday in Allegheny County