District 8 Projects - Franklin County

Route 30 over West Branch of Conococheague Creek Bridge Rehabilitation Project

Project Status

Step 2 of 4

Design

Next Step:  Construction

Public Outreach

Public Comment Period

The public comment period, where the community is encouraged to respond with questions and concerns will be from April 21, 2025 through May 23, 2025

Virtual Plans Display

​The virtual plans display will be available online from April 21, 2025 through May 23, 2025

Project Overview

County: Franklin
Municipality: Peters Township
State Route: SR 0030-158
Local Name: Route 30 (Lincoln Highway) over West Branch of the Conococheague Creek
Project Type: Bridge Rehabilitation
MPMS Number: 117144
Proposed Construction Start: June 2027
Proposed Construction End: September 2027
Last Updated: April 2025

The Route 0030 Section 158 bridge preservation project is located along Route 30 (Lincoln Highway) over West Branch of the Conococheague Creek in Peters Township, Franklin County, approximately 12 miles west of Chambersburg. The purpose of this project is to preserve the bridge and provide continued safe and efficient crossing of Route 30 over West Branch of the Conococheague Creek.

The existing structure was built in 1960 and is a two-span composite prestressed concrete beam bridge supported on full-height concrete abutments at a 65-degree skew.  A wall pier in the center of the bridge is located in the West Branch of the Conococheague Creek.  The bridge length is 118’-3”, measured center-center of bearings from abutment to abutment.

The project involves the replacement of the expansion joints at the abutments and pier, substructure spall repairs and repair of a scour hole at an abutment.  A temporary stream diversion (cofferdam setup) will be constructed to complete the scour repairs.  The overall geometry of the bridge will not be affected by the repairs. 

This section of Lincoln Highway has an average daily traffic volume of 6012 vehicles per day (vpd).

The bridge will remain open to traffic during construction with limited shoulder closures during the day to install scour protection under the bridge and repair the substructures.  Half width bridge closures will occur at night to allow for the joint replacement using an alternating traffic pattern in one lane with flaggers.

There are no overhead utilities present at the site.

The project is currently in design, and construction work is anticipated to begin in Spring 2027 and last approximately 3 months.

The purpose of the plans display is to introduce the project and solicit public input, questions, or concerns regarding the project.​

Additional Project Information

Project Description

The SR 0030 Section 158 bridge preservation project is located along Route 30 (Lincoln Highway) over West Branch of the Conococheague Creek in Peters Township, Franklin County, approximately 12 miles west of Chambersburg. The purpose of this project is to preserve the bridge and provide continued safe and efficient crossing of Route 30 over West Branch of the Conococheague Creek.

The project involves the replacement of the expansion joints at the abutments and pier, substructure spall repairs and repair of a scour hole at an abutment  A temporary stream diversion (cofferdam setup) will be constructed to complete the scour repairs.  The overall geometry of the bridge will not be affected by the repairs. 

This section of Lincoln Highway has an average daily traffic volume of 6012 vehicles per day (vpd).

Environmental

The project is located in a rural setting with terrain varying from level to rolling.  The northern quadrant is maintained floodplain with a pavilion.  The eastern quadrant is athletic fields, the southern quadrant is low-lying flood plains, and the western quadrant Is floodplains.  There are no bicycle or pedestrian facilities for this route.  Other environmental efforts for the project include investigating historical, archeological and aquatic resources as well as threatened and endangered species. 

Utilities

There are no overhead utilities present at the site.

Right-of-way

Temporary right-of-way acquisitions are anticipated to allow the construction of the project. 

Maintenance and Protection of Traffic

The bridge will remain open to traffic during construction with limited shoulder closures during the day to install scour protection under the bridge and repair the substructures.  Half width bridge closures will occur at night to allow for the joint replacement using an alternating traffic pattern in one lane with flaggers.

Schedule and Cost

Overall construction is anticipated to last approximately 3 months during the spring and summer of 2027 at an estimated cost of $400,000.

Contact Information

Robert Nuss
Project manager
717-516-7597
c-ronuss@pa.gov

David M. Thompson
Media Contact
(717) 787-1446
dmthompson@pa.gov

Accessibility

The project documents can be made available in alternative languages or formats if requested. If you need translation or interpretation services, have special needs, or have concerns that require individual attention, please contact the PennDOT Project Manager listed above.

Title VI

Pursuant to the Title VI of the Civil Rights Act of 1964, PennDOT does not discriminate on the basis of race, color, national origin, gender, age, or disability. If you feel that you have been denied the benefits of, or participation in a PennDOT program or activity, you may contact the PennDOT, Bureau of Equal Opportunity, DBE/Title VI Division at 717-787-5891.